Custom Brewery Tank Project Walkthrough

Custom Brewery Tank Project Walkthrough: From Concept to Commissioning

Custom brewery tanks are at the heart of modern craft brewing. While standard, off-the-shelf tanks may work for some breweries, many operations eventually reach a point where custom tank solutions are the only practical way to improve efficiency, product quality, and scalability. Ceiling height limits, unique beer styles, expansion plans, utility constraints, and workflow preferences often require tanks that are designed specifically for a brewery’s needs.

This article provides a full walkthrough of a custom brewery tank project, following a realistic brewery scenario from the initial idea to final commissioning. Along the way, we’ll explain key decisions, common challenges, timelines, and best practices—so you can better understand what goes into a custom tank project and how to manage one successfully.Craft Brewing Equipment Manufacturers

Project Background: Why the Brewery Needed Custom Tanks

Let’s start with a realistic scenario.

A regional craft brewery had been operating successfully for several years with a standard 10 BBL system and a mix of off-the-shelf fermenters. As demand grew, the brewery faced several challenges:

Fermentation capacity was limiting production

Tank heights did not fully utilize available ceiling space

Certain beer styles (high-gravity ales and fruit beers) required more headspace and specialized fittings

Cleaning and turnaround times were becoming inefficient

Expansion space existed, but standard tanks didn’t fit the layout

Rather than replacing everything with larger standard tanks, the brewery decided to invest in a custom brewery tank project designed around its specific building, brewing process, and growth plan.

Phase One: Defining Requirements and Objectives

Every successful custom tank project starts with clear requirements. Before contacting manufacturers, the brewery team defined their goals.

Key Questions Asked Internally

What is our target batch size for the next 5–10 years?

How many fermenters and brite tanks do we need?

Which beer styles drive our production volume?

Are we prioritizing faster tank turns or longer conditioning?

What are our physical constraints (ceiling height, floor load, door width)?

How will these tanks integrate with existing utilities?

Finalized Project Goals

Add four custom 30 BBL fermenters and two 30 BBL brite tanks

Maximize vertical space without exceeding ceiling limits

Improve CIP efficiency and reduce cleaning time

Support high-pressure fermentation and in-tank carbonation

Prepare the cellar for future automation upgrades

Having these goals documented made communication with equipment manufacturers far more effective.

Phase Two: Site Evaluation and Layout Planning

Custom tanks must fit the brewery—not the other way around.

On-Site Measurements

The brewery carefully measured:

Clear ceiling height (including lighting, ductwork, and sprinklers)

Floor slope and drain placement

Column spacing and aisle widths

Door dimensions for tank delivery

Utility access points (glycol, water, compressed air, CO₂)

These measurements were shared with the manufacturer to avoid costly surprises later.

Layout Optimization

Working with CAD drawings, the team evaluated:

Tank spacing for safe access and cleaning

Hose routing and transfer paths

Forklift and pallet movement

Future expansion zones

Custom tank diameter and cone angles were adjusted to maximize volume while preserving safe working clearances.

Phase Three: Custom Tank Design & Engineering

This is where custom projects differ most from standard purchases.

Tank Design Decisions

Tank height and diameter

Taller tanks allowed more volume without increasing footprint

Diameter was limited by door access and aisle clearance

Cone angle

Steeper cones for improved yeast harvesting

Optimized racking arm performance

Pressure rating

Designed for higher pressure to support spunding and carbonation

Included certified pressure relief and vacuum valves

Jackets and insulation

Multi-zone glycol jackets for precise temperature control

Full polyurethane insulation to reduce energy use

Ports and fittings

Extra tri-clamp ports for fruit additions and dry hopping

Dedicated CIP return ports

Sample valves positioned for safe access

Large manways for inspection and manual adjunct additions

Engineering Review

Before fabrication began:

Detailed drawings were reviewed line by line

Weld standards and surface finishes were confirmed

Utility connections were matched to existing systems

Any changes were finalized to avoid delays

This step is critical—late design changes are one of the biggest causes of extended lead times.

Phase Four: Fabrication of Custom Brewery Tanks

Once designs were approved, fabrication began.

Material Preparation

Food-grade stainless steel sheets were cut and rolled

Cones and shells were formed to precise tolerances

Fittings and ferrules were prepared for welding

Welding & Assembly

Internal and external welds were performed by skilled fabricators

Welds were ground and polished to sanitary standards

Jackets were pressure-tested before insulation

Quality Control

Throughout fabrication:

Welds were visually inspected

Dimensional checks ensured exact height and diameter

Pressure tests verified tank integrity

Surface finish inspections ensured cleanability

Photos and progress updates were shared with the brewery to maintain transparency.

Phase Five: Testing, Finishing, and Pre-Shipment Preparation

Before shipping, each custom tank underwent final checks.

Testing Procedures

Hydrostatic pressure testing

Jacket leak testing

Valve and fitting verification

Accessory installation (spray balls, racking arms, sensors)

Finishing

Exterior cladding installed

Insulation sealed

Nameplates and documentation prepared

Tanks cleaned and dried for transport

At this stage, the tanks were effectively production-ready.

Phase Six: Shipping and Delivery Planning

Custom brewery tanks are large, heavy, and delicate.

Logistics Considerations

Oversized freight planning

Protective crating and padding

Delivery route verification

Coordination with brewery staff and contractors

The brewery ensured:

A forklift and rigging crew were scheduled

Floor protection was installed

Doorways were cleared and measured again

Proper planning prevented damage and delays during unloading.

Phase Seven: Installation and Utility Connections

Once delivered, installation began immediately.

Tank Positioning

Tanks were set according to layout drawings

Leveling was carefully adjusted for proper drainage

Clearances were checked for safety and compliance

Utility Hookups

Glycol lines connected and insulated

CIP lines integrated into existing system

CO₂ and compressed air connected

Sensors and gauges wired to control panels

Because the tanks were custom-designed for the space, installation proceeded smoothly without rework.

Phase Eight: Commissioning and First Use

Commissioning is the final step before brewing.

Commissioning Checklist

Pressure testing on-site

Glycol flow verification

Temperature control calibration

CIP cycle testing

Valve and PRV checks

First Cleaning Cycle

Before beer entered the tanks:

Full CIP cycles were run

Flow patterns were observed

Spray ball coverage was confirmed

First Fermentation

The brewery chose a familiar flagship beer for the first fill to:

Validate fermentation performance

Monitor temperature stability

Evaluate yeast harvesting

Check carbonation capability

Results showed improved consistency and reduced turnaround time compared to the old tanks.

Project Results: What the Brewery Achieved

After the custom tank project was completed, the brewery saw measurable benefits:

Operational Improvements

Increased fermentation capacity without expanding footprint

Faster cleaning and turnaround times

Improved temperature stability

Better yeast management

Financial Impact

Higher throughput without increasing brew days

Lower energy usage due to improved insulation

Reduced need for temporary tanks or contract brewing

Long-Term Flexibility

Tanks designed to support new beer styles

Ports available for future automation upgrades

Layout ready for additional expansion

Lessons Learned from the Custom Tank Project

This walkthrough highlights several key lessons:

Define requirements early

Clear goals prevent costly redesigns.

Measure everything twice

Site constraints drive custom design.

Review drawings carefully

Small details matter in daily operations.

Plan logistics in advance

Delivery and installation are as important as fabrication.

Think long-term

Custom tanks should serve future growth, not just current needs.

Conclusion: Why Micet Is a Strong Partner for Custom Brewery Tank Projects

A successful custom brewery tank project requires more than stainless steel—it requires engineering expertise, clear communication, reliable fabrication, and project coordination.

Micet is well-positioned to support breweries through custom tank projects like the one outlined above. Their strengths include:

Custom-designed fermentation and brite tanks

Strong fabrication standards and sanitary finishes

Engineering support from layout through commissioning

Clear lead time communication

Scalable solutions for growing breweries

Whether you’re expanding capacity, optimizing an existing cellar, or building a new brewery from scratch, Micet’s custom brewery tank solutions can help you achieve efficient, future-ready production with confidence.

FAQs

  1. How long does a custom brewery tank project usually take?

From design approval to delivery, most custom brewery tank projects take 8–16 weeks, depending on tank size, complexity, certifications, and shipping distance. Additional time is required for installation and commissioning.

  1. Are custom brewery tanks much more expensive than standard tanks?

Custom tanks often cost more upfront, but they frequently reduce long-term costs by improving efficiency, maximizing space, and minimizing future modifications. For many breweries, the ROI justifies the investment.

  1. What information should I prepare before ordering custom tanks?

You should prepare:

Target batch size and tank volume

Ceiling height and floor layout

Utility specifications

Beer styles and process requirements

Expansion plans

This information allows manufacturers to design tanks that truly fit your brewery.Taba Squishy

Share this article
Shareable URL
Prev Post

The Quickest Online Path to Emergency Preparedness

Next Post

How Apollo Scraper Supports Scalable B2B Lead Collection?

Read next